Project Status

Total Volume of Product Recovered

2021 Year to Date: 33,222 gallons
Life of Project: 13,119,251 gallons
Last Updated: Tuesday, November 30, 2021

status status status

2019/2020 Milestones/Activities
As of December 31, 2020, more than 13 million gallons of petroleum product has been recovered, and over 6 billion gallons of groundwater has been recovered and treated from the three sites comprising the Greenpoint Petroleum Remediation Project. In 2020, the project recovered a total of approximately 47,830 gallons of product, while recovering and treating over 350 million gallons of groundwater to Clean Water Act standards.

ExxonMobil Greenpoint Petroleum Remediation Project (EMGPRP – S224150)
ExxonMobil continues to operate two product and groundwater treatment systems, the on-site recovery and containment system (RCS) located on Kingsland Yard (OU4) and the off-site free-product recovery system (ORS) located at the corner of Bridgewater and Monitor streets (OU7). Typical routine maintenance of both systems includes critical safety device (CSD) checks, acid cleaning of the air strippers, carbon change-outs, filter bag replacement, system inspections, soil vapor extraction (SVE) system sampling, bimonthly discharge monitoring report (DMR) sampling, and weekly operation and maintenance (O&M) task lists.

In November 2020, ExxonMobil began the installation of a 2,000-gallon cone bottom settling tank at the RCS to replace the existing settling tank equipment, as well as replace/upgrade other associated equipment, piping, valves, and controls. This work is expected to be completed in the first half of 2021.

The 2016 Monitor Street IRM Work Plan includes the construction and installation of engineering controls within the 306 North Henry Street property now owned by Broadway Stages. ExxonMobil oversaw construction activities performed by the property owner and the installation of the passive vapor mitigation system and vapor barrier system inside most of the building in 2017 and 2018. Due to a series of NYCDOB stop work orders (SWOs), construction of the center studio remains incomplete, but once the SWOs are lifted and construction resumes, ExxonMobil will continue to oversee the installation of the required additional engineering control elements.

With the significant reduction in the off-site (OU7&8) free-product plume size and volume, ExxonMobil has begun the process of evaluating recovery well metrics of individual recovery wells to determine when they will request to NYSDEC to shut down a well because the well is no longer recovering a significant volume of free-product. Once ExxonMobil believes a well meets all criteria for shutdown, they will submit a formal shutdown request to NYSDEC detailing the evaluation of each criteria, as well as an evaluation of potential impacts of the shutdown on hydraulic control based on groundwater modeling. ExxonMobil also periodically evaluates recovery wells for redevelopment when the specific capacity around the well suggests there are performance issues causing the decreased free-product recovery at the well.

In August 2018, NYSDEC approved ExxonMobil to enhance free-product recovery on the Kingsland Yard property by installing a new pressure-pulse waterflooding injection well network to increase the hydraulic gradient and product movement toward recovery wells. Trenching and installation of pumping wells and vaults for the waterflooding program began in August 2018, with the majority of the construction work completed by the end of December 2018. The waterflooding program injection activities began in May 2019 and are currently active at the site.

In 2017, NYSDEC approved an Interim Remedial Measures Work Plan to delineate and excavate areas where Total Petroleum Hydrocarbon concentrations exceed site-specific cleanup criteria, delineation activities in the North Henry, Monitor, and Kingsland Yards. Excavation activities began in Monitor Yard in December 2017, and work shifted to Kingsland Yard in 2018 once the Monitor Yard work was complete. Petroleum-contaminated soil was temporarily stockpiled on-site before being transported off-site for proper disposal. Contaminated soil removal work was completed in April 2018 except for two excavation areas within Kingsland Yard (N and O) that were inaccessible as the result of stockpiled clean fill for use on other projects including the OU-3 PCB remediation. With the restoration of the OU-3 remediation work complete, ExxonMobil plans to excavate and remediate the N and O areas in 2021.

Former Paragon Oil Terminal (S224083) and Apollo Street Creek Parcels (S224122)
Through April 2018, Chevron-Texaco continued to operate a total fluids recovery (TFR) system where 17 recovery wells pumped both groundwater and product into an onsite treatment system that collected the product and treated groundwater before discharging into sanitary. Starting in April 2018, both TFR and the VPR systems were shut down to construct system upgrades that were outlined and approved by the NYSDEC. TFR system upgrades include demolition of the existing TFR system buildings and replacement with a new, expanded remediation system that can handle additional flow from new recovery wells with improved telemetry. The system upgrades were completed in February 2019 and the upgraded system operated on a limited basis until the treatment system began full runtime operation on August 19, 2019.

Typical routine maintenance of the TFR system includes backwashing the clay and carbon units, changing out spent clay and carbon, and replacing filter bags. Recovery well pumps are pulled and cleaned as needed, typically every six weeks to two months, based on performance metrics. Non-routine maintenance performed in 2020 included the replacement of the 1,000-gallon product holding tank in March 2020.

Chevron-Texaco also operated a vapor-phase recovery (VPR) system to remove vapor contamination from beneath the Empire Merchants’ buildings and aid in the reduction of product accumulations in and around the existing recovery well network. The VPR is a relatively low-vacuum system aimed at volatilizing PSH in extraction wells and reducing the PSH loading into the water treatment system. The catalytic oxidizer system had been off-line for approximately six months in 2020 due to blower and motor issues. The equipment was sent to the manufacturer for repair and the repaired equipment was installed and system running in late 2020.

As part of the treatment system operation and maintenance, Chevron-Texaco routinely performs bulkhead inspections and maintains the boom containment systems along both the former Paragon Oil Terminal and Apollo Street bulkheads. Chevron-Texaco continued to inspect and reseal bulkhead seams with a marine epoxy on a monthly basis from April until October, and containment booms were evaluated/adjusted on a quarterly basis in 2019 and 2020. One sheen was observed within containment booms along the creek bulkhead during 2019 oversight events, but no sheens were observed within containment booms in 2020. No sheens were observed in Newtown Creek outside the containment boom system in either 2019 or 2020.

Starting in April 2018, both TFR and the VPR systems were shut down to construct system upgrades that were outlined and approved by the NYSDEC. TFR system upgrades include demolition of the existing TFR system buildings and replacement with a new, expanded remediation system that can handle additional flow from new recovery wells with improved telemetry. As of December 31, 2018, work on the system upgrades was still ongoing, with work expected to be complete and both systems operational in early 2019.

As part of the treatment system operation and maintenance, Chevron-Texaco routinely performs bulkhead inspections and maintains the boom containment systems along both the former Paragon Oil Terminal and Apollo Street bulkheads. Chevron-Texaco continued to reseal bulkhead seams with a marine epoxy and adjusting containment boom on a quarterly basis in 2018. One sheen was observed within containment booms along the creek bulkhead during oversight events in 2018, but no sheens were observed outside the containment boom system.

Indoor monitoring wells in the Empire Merchants and the Apollo Street warehouses are inspected monthly, with slab maintenance activities (cracks, seams, and joints are repaired and resealed) are performed twice a year to prevent the possibility of vapor intrusion during the semiannual warehouse shutdowns (January and July). Ambient air quality in the warehouses is monitored on a semi-annual basis during the shutdowns, with a total of 18 air samples typically collected across the site to ensure air quality inside the building is safe. Product and groundwater sampling are also performed at select indoor monitoring wells during the warehouse shutdown events.

KM Terminal (formerly BP Terminal) (S224082)
In 2020, KM continued the operation of 13 product recovery wells and a groundwater treatment system that was installed in 2014. Typical routine recovery system maintenance activities include system alarm and integrity checks, bag filter changes, adjustments to the chemical feed for iron reduction, acid cleaning of the air stripper, and cleaning the product pump intake screens.

Due to persistent LNAPL thicknesses greater than 3 feet in monitoring wells OW-11 and MW-6, both wells were outfitted with a temporary product recovery system that operates independently of the full-scale recovery system in 2016. Due to consistent product recovery from MW-6, the monitoring well was converted into a permanent recovery well and added to the system in June 2019. Monitoring well OW-11 continues to operate with temporary liquid petroleum hydrocarbon recovery equipment in the well, with 100 gallons of LNAPL recovered in 2020.

KM continued to perform methane screening at various locations on the Terminal Property, but access to some of the locations became limited due to restrictions associated with the COVID-19 pandemic was limited throughout 2020 starting in the Second Quarter 2020. KM also performed an annual site-wide vapor screening event in February 2020 to monitor the levels of methane, oxygen, carbon dioxide, carbon monoxide, hydrogen sulfide, balance, lower explosive limit, barometric pressure, and relative pressure across the site. No vapor readings were identified by the screening events that required further action in 2020.

KM began the process of developing an Alternatives Analysis Report in 2018 that will evaluate remedial alternatives to address any potential significant threats to the public health from the remaining contamination at the site. This report will summarize previous and current site conditions, the current remediation activities, and remedial goals for the site while taking into taken into consideration the current and future use of the site. Following an examination of potential remedial technologies to for each media at the site (groundwater, soil, and air), the report will identify the recommended remedial action for the site going forward. KM submitted a draft report in June 2019 and is currently addressing comments to develop the final report.


This page was last updated on Wednesday, May 5, 2021.